NTPC to borrow $478 million from Japanese banks to fund clean energy - Hindustan Times
close_game
close_game

NTPC to borrow $478 million from Japanese banks to fund clean energy

Chennai | ByReuters | Posted by Ayshee Bhaduri
Oct 28, 2020 10:52 PM IST

Japan Bank for International Co-operation (JBIC) will provide 60% of the loan along with other Japanese commercial banks,including Sumitomo Mitsui Banking Corp, San-In Godo Bank Ltd,and Nanto Bank Ltd will extend the rest of the loan amount

India’s largest electricity generator National Thermal Power Corporation Limited (NTPC Ltd) said on Wednesday it would borrow 50 billion yen ($478 million) from Japanese banks to fund the installation of emission cutting equipment and green energy projects.

Data from the Central Electricity Authority’s (CEA) website shows over 60% of coal-fired utilities have not yet awarded bids to install the emission cutting equipment(HT Archive)
Data from the Central Electricity Authority’s (CEA) website shows over 60% of coal-fired utilities have not yet awarded bids to install the emission cutting equipment(HT Archive)

“The loan proceeds will be utilized by NTPC Ltd, the PSU under Ministry of Power, for funding its capex for Flue Gas Desulphurization (FGD) & Renewable Energy projects,” government-run NTPC said in a statement.

Hindustan Times - your fastest source for breaking news! Read now.

Flue Gas Desulphurization (FGD) units cut emissions of sulphur dioxides - which are linked to lung diseases and acid rain - from coal-fired power plants.

Japan Bank for International Co-operation (JBIC) will provide 60% of the loan under its Global Action for Reconciling Economic growth and Environment preservation (GREEN) initiative, NTPC said in a statement.

Other Japanese commercial banks, including Sumitomo Mitsui Banking Corp, San-In Godo Bank Ltd and Nanto Bank Ltd, will extend the rest of the loan amount.

India has a phased plan for plants to comply with emission norms, with deadlines extending to the end of December 2022.

Data from the Central Electricity Authority’s (CEA) website shows over 60% of coal-fired utilities have not yet awarded bids to install the emission cutting equipment.

Nearly three quarters of the plants that have awarded bids for installation of FGDs are NTPC-run plants, the data shows.

The Association of Power Producers (APP), an industry lobby group, estimates that installation of FGDs takes at least 27 months, putting over 100 GW of coal-fired utilities - most of which are operated by private companies and provincial governments - at risk of non-compliance.

Over a sixth of the plants have already missed a deadline to install FGDs, according to the CEA data.

India, currently struggling with some of the worst air pollution levels on earth, has already extended the deadline for its utilities to meet emissions standards twice, after extensive lobbying by the APP.

Unlock a world of Benefits with HT! From insightful newsletters to real-time news alerts and a personalized news feed – it's all here, just a click away!- Login Now!
Stay informed on Business News along with Gold Rates Today, India News and other related updates on Hindustan Times Website and APPs
SHARE THIS ARTICLE ON
Share this article
SHARE
Story Saved
Live Score
OPEN APP
Saved Articles
Following
My Reads
Sign out
New Delhi 0C
Thursday, March 28, 2024
Start 14 Days Free Trial Subscribe Now
Follow Us On