Our cost increased by Rs1,850 crore: Delhi Government on Metro phase 4

Hindustan Times, New Delhi | By
Apr 04, 2019 05:16 AM IST

Stuck for more than two years, the project had on March 7 got the go-ahead from the Union Cabinet, which approved only three corridors— Aerocity to Tughlakabad, Janakpuri to RK Ashram and Mukundpur to Maujpur.

A day after the ministry of housing and urban affairs (MoHUA) blamed the Delhi government for delaying the Metro Phase-IV project, the latter on Wednesday said the city administration’s cost in the expansion plan had indeed increased by about Rs1,850 crore.

The Delhi government had objected that its share of cost to build the three corridors had increased to <span class='webrupee'>₹</span>7,844.70 crore from <span class='webrupee'>₹</span>5,994.50 crore.(HT PHOTO)
The Delhi government had objected that its share of cost to build the three corridors had increased to 7,844.70 crore from 5,994.50 crore.(HT PHOTO)

In a statement issued by transport minister Kailash Gahlot’s office, the government accused the Delhi Metro Rail Corporation (DMRC) of repeatedly changing the cost of Phase-IV, which includes six corridors.

Hindustan Times - your fastest source for breaking news! Read now.

Stuck for more than two years, the project had on March 7 got the go-ahead from the Union Cabinet, which approved only three corridors— Aerocity to Tughlakabad, Janakpuri to RK Ashram and Mukundpur to Maujpur.“The statement issued by MoHUA on Tuesday seeks to justify the unilateral decisions taken by the government of India regarding a revision in the overall cost and various cost components of Delhi Metro Phase-IV, as well as an increase in the liability of GNCTD by about Rs1,850 crore, without taking the Government of NCT of Delhi into confidence,” read Delhi government statement.

The Delhi government had objected that its share of cost to build the three corridors had increased to 7,844.70 crore from 5,994.50 crore. In response, the ministry had said, “As per the proposal for the three corridors submitted by DMRC in January 2018 (the cost of which was proportionate to the cost of the six corridors approved by Delhi Cabinet earlier), the total liability of the city government was 8,872 crore, whereas, as per the cost approved by the Centre in March, the total liability of Delhi government had come down by more than 1,000 cr to 7,844 crores.”

Unveiling 'Elections 2024: The Big Picture', a fresh segment in HT's talk show 'The Interview with Kumkum Chadha', where leaders across the political spectrum discuss the upcoming general elections. Watch now!
SHARE THIS ARTICLE ON
Share this article
SHARE
Story Saved
Live Score
OPEN APP
Saved Articles
Following
My Reads
Sign out
New Delhi 0C
Friday, March 29, 2024
Start 14 Days Free Trial Subscribe Now
Follow Us On