No more daytime flights as Kochi airport work is set to begin | Latest News India - Hindustan Times
close_game
close_game

No more daytime flights as Kochi airport work is set to begin

Kochi | ByPress Trust of India
Nov 18, 2019 08:59 PM IST

Cochin International Airport Ltd (CIAL) has started the preparatory work for the project well in advance and thereby ensured the minimal cancellation of services with the co-operation of the airlines, the statement said.

The four-month-long runway re- surfacing work at Kochi Airport is set to start on Wednesday and there would be flights from 10 AM to 6 PM till March 28, 2020.

Cochin International Airport Ltd (CIAL) T3 airport in Kochi.(PTI Photo)
Cochin International Airport Ltd (CIAL) T3 airport in Kochi.(PTI Photo)

Since almost all services have already been re- scheduled between 6 PM and 10 AM, the project period would see cancellation of only five services during the major runway re-surfacing period, a statement from the airport said on Monday.

Hindustan Times - your fastest source for breaking news! Read now.

Cochin International Airport Ltd (CIAL) has started the preparatory work for the project well in advance and thereby ensured the minimal cancellation of services with the co-operation of the airlines, the statement said.

The winter schedule which became effective from the last week of October has already adjusted the services to the available operational time, which sees the cancellation of only one service in international sector-Maldives service operated by Spice Jet- and four services in domestic sector.

Domestic sector is going to have only four cancellations, it said.

CIAL - the seventh busiest airport in the country- - handles 240 aircraft movements and 30,000 passengers a day, expects a rush in early morning and early evening hours as the operational time is going to be stipulated from 24 hrs to 16 hrs.

In view of it, CIAL has decided to increase the check-in time to 3 hrs for the domestic passengers and 4 hrs for the international passengers, the statement said.

Arrangements were already made to ensure hassle-free passenger movement with the help of Customs, Immigration, ground-handling agencies.

The CISF, which manages airport security has deployed 100 additional security men raising their total strength to 950 at Kochi airport.

The agency also decided to deploy another 400 security personnel in the weeks to come.

The airport which started functioning in 1999 underwent first runway re-surfacing work in 2009.

The re-surfing is done to ensure the desired level of friction to facilitate precision landing for the aircraft.

An area of five lakh square meter comprising the 3,400-metre-long runway, with a width of 60 M, and the taxiway, taxiway links would be overhauled during the period.

Simultaneously, CIAL is realigning the lighting system - fixing of central line lights every 15 metres, introduction of new lights at touch-down zones and parking bays, the statement said.

CIAL is spending around 150 crore for the project and expect to complete it as per schedule, it added.

Unveiling Elections 2024: The Big Picture', a fresh segment in HT's talk show 'The Interview with Kumkum Chadha', where leaders across the political spectrum discuss the upcoming general elections. Watch now!

Get Current Updates on India News, Election 2024, Arvind Kejriwal News Live, Bihar Board 10th Result 2024 Live along with Latest News and Top Headlines from India and around the world.
SHARE THIS ARTICLE ON
Share this article
SHARE
Story Saved
Live Score
OPEN APP
Saved Articles
Following
My Reads
Sign out
New Delhi 0C
Friday, March 29, 2024
Start 14 Days Free Trial Subscribe Now
Follow Us On