State lost Rs 1,000 cr in project cost overrun

None | ByManish Dixit, Bhopal
Mar 28, 2006 03:55 PM IST

MADHYA PRADESH could have saved Rs 1,000 crore had the successive State governments stuck to time frame for completing various schemes.

MADHYA PRADESH could have saved Rs 1,000 crore had the successive State governments stuck to time frame for completing various schemes.

HT Image
HT Image

In its latest report, even Comptroller and Auditor General (CAG) mentioned that there were 436 uncompleted schemes involving capital expenditure of Rs 9,031 crore.

Hindustan Times - your fastest source for breaking news! Read now.

So tardy has been the pace of projects in the State that Bansagr project, which was to be completed in 1983, is still uncompleted.

The project was inaugurated in 1978 by the then prime minister Morarji Desai. The cost overrun is mostly prevalent in schemes of Water Resources Department, though Schemes in PWD, PHED etc. don’t fare any better either.

Sources in Water Resources Department said apart from Bansagar, Maan & Jobat , Bargi,  Rajghat , Mahi and Bhavantari projects are also other glaring examples of time and cost overrun.

Sensing seriousness of the matter, Chief Secretary Rakesh Sahni recently wrote to all senior officers.He said while reviewing work of various departments it has come to his notice that cost of many schemes increased considerably because the departments failed to complete them in stipulated time.

Sahni directed senior officers to ensure that special efforts are made to complete the unfinished schemes. He also directed all departments to prepare a comprehensive list of such schemes, which have exceeded time limit by one year or more, and try to find out reasons why these schemes were not completed on time.

The Chief Secretary further asked the departmental heads to prepare programmes to completed these schemes in the next fiscal i.e. 2006-07 and send a detail report with information about such schemes, reason of delay and cost overrun by the end of this month.

Detailed information about number of such schemes along with increase in their cost would be available only after all departments would send their reports to the Chief Secretary.

Unveiling Elections 2024: The Big Picture', a fresh segment in HT's talk show 'The Interview with Kumkum Chadha', where leaders across the political spectrum discuss the upcoming general elections. Watch now!

Get Current Updates on India News, Election 2024, Arvind Kejriwal News Live, Bihar Board 10th Result 2024 Live along with Latest News and Top Headlines from India and around the world.
SHARE THIS ARTICLE ON
Share this article
SHARE
Story Saved
Live Score
OPEN APP
Saved Articles
Following
My Reads
Sign out
New Delhi 0C
Friday, March 29, 2024
Start 14 Days Free Trial Subscribe Now
Follow Us On