BMC panel to go into CAG criticism on sewage project | Mumbai news - Hindustan Times
close_game
close_game

BMC panel to go into CAG criticism on sewage project

Hindustan Times | By, Mumbai
Jun 29, 2016 12:21 AM IST

HT had reported in December that the CAG had severely criticised the project for financial irregularities, faulty design and technology, incorrect data and incompetence

The Brihanmumbai Municipal Corporation has appointed a three-member committee to go into the work done by an international consortium led by Mott Macdonald for its ambitious Rs12,000-crore Mumbai Sewerage Disposal Project (MSDP-2) that has come under fire from the Comptroller and Auditor General (CAG).

The project envisages the setting up of seven sewage treatment plants — at Colaba, Worli, Bandra, Versova, Malad, Ghatkopar and Bhandup — and upgrading existing networks to cover the entire city by 2025.(File photo)
The project envisages the setting up of seven sewage treatment plants — at Colaba, Worli, Bandra, Versova, Malad, Ghatkopar and Bhandup — and upgrading existing networks to cover the entire city by 2025.(File photo)

The probe was ordered last week and the report is expected in 15 days.

Hindustan Times - your fastest source for breaking news! Read now.

The committee headed by deputy chief engineer (Mumbai Sewage Disposal Project) includes the deputy law officer and the deputy chief accountant (finance). It will probe all the problems mentioned in the CAG report  and fix responsibility for any wrongdoing. It will also consider if the Rs143 crore paid to the consultant was justified.

Read: CAG slams BMC, contractor over Rs12,000-cr sewage project

Additional municipal commissioner Dr Sanjay Mukherjee confirmed the development.

The project envisages the setting up of seven sewage treatment plants — at Colaba, Worli, Bandra, Versova, Malad, Ghatkopar and Bhandup — and upgrading existing networks to cover the entire city by 2025.

The contract to prepare the master plan was awarded in 1999 and it was completed in 2002. However, after the Maharashtra Pollution Control Board changed pollution norms for treatment plants in 2007, the job of preparing the plan for the project was again awarded to the same consortium.

But eight years later, the plan remained incomplete despite a three-year extension. In 2015, the BMC decided to cancel the contract and choose another contractor.

But by this time, the cost of the project had more than doubled from Rs5,000 crore to Rs12,000 crore. The CAG note also pointed to deficiencies in the master plan at the time of execution.

Of the seven locations, only the treatment plant at Colaba has seen some progress, with the tenders being allotted for construction.

SHARE THIS ARTICLE ON
Share this article
  • ABOUT THE AUTHOR
    author-default-90x90

    Chetna Yerunkar is a Senior Correspondent for Hindustan Times, Mumbai. She is currently covering civic and governance issues for the Mumbai bureau.